Equipment Decommissioning


Project Summary: AM Technical Solutions was hired by Facility to decommission the LAB. AM Technical Solutions removed all arsenic contaminated duct, all toxic, and bulk gas systems. AM Technical Solutions also completed final cleaning of laboratory to assure there were no contaminated work spaces. Problems Encountered during the Project : None

T. B.
Semiconductor Research Facility

SERVICES

  • Project Schedule Management
  • Project Cost Support
  • Project Quality Support
  • Equipment Installation / Deinstallation
  • Project Coordination
  • Decomissioning
  • Defacilitization
  • Certificate of Acceptability
  • Control & Compliance
  • Turnover Control & Documentation
  • Quality Assurance / Quality Control
  • Safety Surveys, Inspection, & Reporting
  • Safety Training Programs & Certifications
  • Contractor Supervision / Audits
  • Safety Program Development & Management
  • OSHA & Other Regulatory Review